Crashing is

A. Abandoning the project
B. Completing the project with all possible haste
C. Reduction of duration for a few of the activities
D. Reduction the cost of the project with all needful modification

Answer: Reduction of duration for a few of the activities

EXPLANATION

Project crashing is a method for shortening the project duration by reducing the time of one (or more) of the critical project activities to less than its normal activity time. This reduction in the normal activity time is referred to as crashing.